Request for activities without dates
Hi there! We make avid use of templates for our projects. I would like to be able to include activities (not tasks) in these templates WITHOUT a set date. That way I can create placeholders for meetings that occur within each step of the project, without having to assign dates before they are set and just simply fill in the date once it has been determined with the client.
Please let me know if my request is unclear!
Comments
-
@Mike van der Valk do you know is this is something we may expect in the future or should I change my workflow for now? :)
0 -
Hi @Roos.Eversdijk , a set date will continue to be a required field in activities for the foreseeable future. But your feedback has been noted by our team.
0 -
Hi Manuel, that's a shame to hear but thanks for your reply! We will figure out an alternative.